 1.
ETHIOPIA TELECOM PROJECT
  Customer : TCIL (Telecommunications Consultants India Ltd). Enduser: Ethiopia Telecom.
  Scope :
Supply of Nokia 34 Mbit/s (1+1) Protected OLTE system and associated Multiplexer equipment.
  Status : Completed in September, 2006
 
 2.
12” SUDAN PIPELINE PROJECT
  Customer : Larsen & Toubro, ONGC Videsh Limited. Enduser: SPPC, Sudan.
  Scope :
Turnkey Scope for system design engineering, integration of ~ Marconi SDH STM4, Nokia Primary Multiplex Equipment, EPABX & VHF Trunk Radio System. Factory Acceptance Testing, Training, Installation, Testing and Commissioning of the Transmission & Radio equipment for 12” Sudan Pipeline Project of SPPC.
  Status : Project completed November, 2005.
 
 3.
SOHAR & SALALAH GAS PIPELINE TRANSMISSION SYSTEM PROJECT
  Customer : WWW. Projects Pty. Ltd. Enduser: Oman Gas Company.
  Scope :
Design, Integration, factory acceptance testing and commissioning of a STM-1 and Loop Protected PDH Transmission System.
  Status : Completed.
 
4.
SBV-0 - RAA STM NETWORK PROJECT
  Customer : WWW. Projects Pty. Ltd. Enduser: Qatar Petroleum.
  Scope :
Design, Integration, installation, testing and commissioning of a STM-4 and STM-1 transmission system with associated PDH equipment.
  Status : Completed in February, 2003
 
 5.

NEXTGEN NETWORKS PROJECTS, AUSTRALIA.

  Customer : CommTel D.N.S., Australia. Enduser : NextGen Networks Pty. Ltd. Australia.
  Scope :
Verification & validation of DWDM based fibre optic transmission system upto capacity of 2.4 Tbit/s (Terabits) connecting five Primary nodes at Melbourne, Sydney, Brisbane, Adelaide & Perth.
  Status : Completed.

 6.

EASTERN SDH RING & ASSOCIATED PDH NETWORK PROJECT, QATAR

  Customer : WWW. Projects Pty. Ltd. Enduser: Qatar General Petroleum Corporation.
  Scope :
Design, Integration, installation, testing and commissioning of a STM-4 and STM-1 transmission system for Eastern Ring Project along with associated PDH spur routes & 18 GHz Digital Microwave Radio Links.
  Status : Completed in January, 2002
 
7.
SNOWY MOUNTAINS PROJECT
  Customer : CommTel , Australia. Enduser: Snowy Mountains Hydroelectric Authority.
  Scope :
Installation & Commissioning of 2 Mbit/s PDH equipment for their existing Telecom Network.
  Status : Completed in December, 2000
 
 8.
DUKHAN STM RING & ASSOCIATED PDH NETWORK PROJECT, QATAR
  Customer : WWW. Projects Pty. Ltd. Enduser : Qatar General Petroleum Corporation.
  Scope :
Design, Integration, installation, testing and commissioning of a STM-4 and STM-1 transmission system for Dukhan Gas fields along with associated PDH spur routes.
  Status : Completed in June, 2000
 
 9.
Y2K UPGRADE OF TRANSMISSION MANAGEMENT COMPUTER (NEPAL)
  Customer : Nokia Limited. Enduser : Nepal Telecommunication Corporation.
  Scope :
Services for upgradation of Transmission Management Computer of NTC to make it Y2K compliant.
  Status : Completed in the Month of December, 1999.
10.
HUBARA POWER STATION PROJECT, OMAN
  Customer : WWW. Projects Pty. Ltd. Enduser : Petroleum Development Oman.
  Scope :
System Design, Integration, Installation, Testing and Commissioning of a 8 Mbit/s digital transmission system including termination of optical fibre cables at 2 terminal ends.
  Status : Completed in September, 1999
 
 11.
NIMR - NIMR WEST PROJECT, OMAN
  Customer : WWW. Projects Pty. Ltd. Enduser : Petroleum Development Oman.
  Scope :
System Design, Integration, Installation, Testing and Commissioning of a 2 Mbit/s digital transmission system including termination of optical fibre cables at 2 terminal ends.
  Status : Completed in July, 1999
 
 12.
AL-NOOR TO NIMR OFC LINK PROJECT, OMAN
  Customer : WWW. Projects Pty. Ltd. Enduser : Petroleum Development Oman.
  Scope :
Supervision of installation of ADSS Optical Fibre cable, jointing, testing and termination along with Installation, Testing and Commissioning of a 2 Mbit/s digital transmission 2 terminal ends.
  Status : Project Completed in May, 1999
 
13.
LNG UPSTREAM GAS PIPELINE PROJECT, OMAN
Customer :
Olex Pty Limited. Enduser : Petroleum Development Oman.
Scope :
Installation, Testing and Commissioning of 34 Mbit/s optical fibre based digital transmission system for a 300 kms long gas pipeline.
  Status : Project Completed in February, 1999
   



     
 
     