STM-1 SYSTEM CONNECTIVITY OF ALWAR AND AJMER LINKS OFGAIL
Customer :
GAIL (India) Ltd.
Scope:
System design, transportation, supply of installation materials, installation, testing and commissioning of STM-1 Syfonet SDH nodes,including configuration of newly installed nodes at the Network Management Centres of GAIL.
Status:
Project Completed in November, 2002.
COCHIN - COIMBATORE - KARUR PIPELINE PROJECT (Fibre Optic Cable Services)
Customer :
Dodsal Limited Enduser: Petronet CCK Limited
Scope:
Optical fibre Cable Testing, Jointing, Termination & Commissioning Services. Supply of FTC (Fibre Termination Closure).
Status:
Project Completed in December, 2001.
BAILADILA - VIZAG SLURRY PIPELINE PROJECT, INDIA
Customer :
Hygrade Pellets Ltd.
Scope:
Consultancy Services for detailed Engineering of Telecom and SCADA Systems.
Status:
Project Completed in September, 2001
COCHIN - COIMBATORE - KARUR PIPELINE PROJECT (Transmission System
Customer :
Nokia Networks OY. Enduser: Petronet CCK Ltd.
Scope:
Design, Integration, Testing, FAT (Factory Acceptance Test)for SDH STM-1 & STM-4 Digital Transmission System along with associated PDH system and documentation.
Status:
Project Completed in December, 2000
Y2K UPGRADE OF TRANSMISSION MANAGEMENT COMPUTER (INDIA)
Customer :
Bharat Petroleum Corporation Limited
Scope:
Supply and upgradation services for upgrading the transmission management computer to make it Y2K compliant. 2 TMC's located at Mumbai and Manmad were upgraded.
Status:
Project Completed in September, 1999.
Y2K UPGRADE OF TRANSMISSION MANAGEMENT COMPUTER (INDIA)
Customer :
Hindustan Petroleum Corporation Limited
Scope:
Supply and upgradation services for upgrading the transmission management computer to make it Y2K compliant. 2 TMC's located at Vizag and Vijayawada were upgraded.
Status:
Project Completed in August, 1999.
Y2K UPGRADE OF TRANSMISSION MANAGEMENT COMPUTER (INDIA)
Customer :
Indian Oil Corporation (Panipat and Sanganer)
Scope:
Supply and upgradation services for upgrading the transmission management computer to make it Y2K compliant. 2 TMC's located at Panipat and Sanganer were upgraded
Status:
Project Completed in May, 1999.
VIZAG-VIJAYAWADA- SECUNDERABAD PIPELINE PROJECT (INDIA)-Maintenance Contract
Customer :
Hindustan Petroleum Corporation Limited
Scope:
Maintenance services for optical fibre based 34 Mbit/s digital transmission system for a 350 kms long oil pipeline. The project also involves repair and return of telecom cards and is monitored on a bi-annual visit basis.
Status:
On going
MUMBAI - MANMAD PIPELINE PROJECT (INDIA)-Maintenance Contract
Customer :
Bharat Petroleum Corporation Limited
Scope:
Maintenance services for optical fibre based 8 Mbit/s digital transmission system for a 250 kms long oil pipeline.
Status:
On going
AMC FOR COCHIN- COIMBATORE-KARUR PIPELINE PROJECT
Customer :
Petronet CCK Limited
Scope:
Annual Maintenance Contract for Nokia SDH STM-1/4 System and Primary Multiplex equipment installed for Cohin-Coimbatore-Karur pipeline project of Petronet CCK Limited
Status:
On going
MAINTENANCE OF DIGITAL RADIO LINK BETWEEN BANDRA & URAN
Customer :
Oil & Natural Gas Corporation Limited
Scope:
Maintenance for hardware and software for 2 GHz digital microwave link between Bandra and Uran (3 Hops). Nokia Equipment.
Status:
Project Completed in 2007
OPTICAL FIBRE MAINTENANCE FOR RIIL PIPELINES (INDIA)
Customer :
Reliance Industrial Infrastructure Limited, RIL-NBD, CPPL
Scope:
Maintenance services for 110 Kms long optical fibre cable jointing and testing for the CPPL and JKPL Pipelines including maintenance of 34Mbps and 8Mbps Telecom System. Repair and return of telecom cards and upgradation of telecom system to 8 & 34 Mbps. It also entails power supply and SCADA System, maintenance of 2 Mbps Telecom System and a 7 Ghz MW Radio link.
Status:
On going
SUPPLY OF NOKIA EQUIPMENT SPARES
Customer :
Petronet CCK Limited
Scope:
Supply of Nokia Synfonet SDH Equipment Spares.
Status:
Delivered in the month of October, 2004.
SUPPLY OF NOKIA EQUIPMENT SPARES
Customer :
GAIL (India) Ltd.
Scope:
Supply of spares for spares for Nokia digital transmission system (Nokia Equipment)
Status:
Equipment delivered in March, 2004.
SUPPLY OF SDH STM-1 EQUIPMENT TO GAIL (India) Ltd.
Customer :
GAIL (India) Ltd.
Scope:
Supply of Synfonet STM-1 SDH equipment for establishing connectivity of Ajmer, Alwar and Dadri for GAILTEL Phase-I Project.
Status:
Equipment delivered in March, 2003.
SUPPLY OF SPARES FOR KBPL PROJECT (INDIA)
Customer :
Indian Oil Corporation Limited
Scope:
Supply of spares for digital transmission system (Nokia Equipment)
Status:
Delivered in the month of March, 2002.
Delivered in the month of March, 2002.
Customer :
Bharat Petroleum Corporation Limited
Scope:
Supply of spares for digital transmission system
Status:
Delivered in the month of January, 2000
SUPPLY OF TELECOMMUNICATION PRODUCTS (QATAR)
Customer :
Consolidated Gulf Co. L.L.C.
Scope:
Supply of krone IDF and accessories along with manufacturing and supply of stub cables for the channel units of digital transmission system.
Status:
Completed in September, 1999
SUPPLY OF SPARES FOR VVPL PROJECT (INDIA)
Customer :
Hindustan Petroleum Corporation Limited
Scope:
Supply of spares for digital transmission system.
Status:
Delivered in the month of April, 1999
 
 

As part of social
responsibility towards
the community in which
we live and flourish, we considered it imperative
to take an initiative which provides us with a
platform to support social causes...
 
 
Company Profile
Commtel Introduction
Technology Papers
Technical Glossaries and Abbreviations
 
 
Maintenance Service (Remote/On-Site Voice/
Web Support) is being offered by the company under this segment.